TRAFFIC ALERT: Construction project on Bridge St. in Chippewa Falls to begin Monday

The State Highway 124 Bridge Street Project is set to begin on Monday. 
Lane closures are expected on Bridge Street in Chippewa Falls.

MGN Online

EAU CLAIRE, Wis. (WISCONSIN DEPARTMENT OF TRANSPORTATION NEWS RELEASE) -- Roadway improvements are scheduled to begin August 18 between the Chippewa River and River Street/Bridge Street roundabout in Chippewa Falls. The project will include new pavement, lighting, curb and gutter and signage.

The project will be done in three stages, with different impacts to motorists:

• During stage 1, the WIS 124 northbound and southbound inside lanes will be closed. This portion is expected to last one week.

• Stage 2, lasting through mid-September, will close the WIS 124 northbound ramp from E. Park Avenue and the Court Street/WIS 124 intersection. During this time, traffic will be shifted to the southbound lanes and will use the temporary crossovers constructed during stage 1.

• The final stage will open Court Street to right-in and right-out maneuvers. During stage 3, traffic will use the northbound lanes while the southbound lanes are being constructed.

The project is expected to be completed by the end of October.


Comments are posted from viewers like you and do not always reflect the views of this station.
powered by Disqus
WEAU 13 NEWS 1907 S. Hastings Way Eau Claire, WI 54701 By Phone: Main Number (715) 835-1313 and (715) 832-3474. Tip Line (715) 839-WEAU - (715) 839-9328 Sports Line (715) 852-1537
Gray Television, Inc. - Copyright © 2002-2014 - Designed by Gray Digital Media - Powered by Clickability 271096211 - weau.com/a?a=271096211